- Construction cost
- 2 M$
- Duration
- 5 months
- Schedule
- September 2021 to January 2022
- Disciplines
- 1 trades
- Client
- Construction Technipro BSL
- Location
- 2S0, avenue Rouleau, Rimouski (QC)
- Project type
- Construction work on the teaching pavilion at the Rimouski Regional Hospital
At a glance
Project description
The project consists of the construction of a pavilion at the Rimouski regional hospital center, the work of which includes, but is not limited to:
Scope of work
Work performed
- Formwork and placement of concrete for the construction of footings and foundation walls
- Formwork and concrete placement for columns, walls and structural slabs of the 4-level reinforced concrete superstructure
- Installation of metals embedded in concrete works for the steel structure
Planning municipal infrastructure work? Get our team’s input.
Request a quoteOn site
Project challenges
- Work to be carried out in the hospital center in full operation
- Protection of occupants and various accesses
- Accessibility at all times to traffic and evacuation areas
Services provided
- Construction management
- Project management
Disciplines
Planning a similar project?
Our team supports municipalities and project owners from design through commissioning.